Project reviews completed from January 15 to February 15 are listed below. These projects have been screened through the internal environmental review process for potential impacts on wetlands, threatened and endangered species, and cultural and archaeological resources etc. Through the review process it was determined that environmental impacts have been kept to a minimum and mitigated as necessary and that they do not meet the criteria for significant actions as defined in the environmental review process and may proceed. All of these projects are in compliance with the Endangered Species Protection Act, Natural Areas Preservation Act, Interagency Wetlands Policy Act and cultural resource statutes.

  • Union County Refuge
    0100434 - This project includes the demolition of a deteriorating building formerly used as the site office. All materials will be removed from the site and disposed of by recycling and/or disposal of materials at an approved landfill. Project was submitted for review on 1-19-01.

  • Volo Bog State Natural Area
    0100303 - This project entails the clean up of a dumpsite located in a ravine at the site. Approximately 90 - 150 cubic yards of scrap metal will be placed into rolloffs or trucks and removed from the site. Project was submitted for review on 1-8-01.

  • Coffeen Lake State Fish & Wildlife Area
    0100717 - This project involves the expansion of the parking lot at the Carlock Point Day Use Area. The existing lot will be increased in size by 25 x 50 feet and be covered with CA 6 rock. Project was submitted for review on 1-26-01.

  • Kinkaid Lake
    0100813 - This project will stabilize severely eroded shorelines at the lake by placing riprap along the existing shoreline from a barge. Filter fabric will be first anchored to the existing foreslope and the stone will be placed to a height of approximately 36" above normal pool. Approximately 2900' of shoreline is expected to be stabilized with this procedure. Project was submitted for review on 2-1-01.

  • Cache River State Natural Area
    0100809 - This project involves the installation of a series of 6-8 riffle weirs in a segment of the river adjacent to Heron Pond. These weirs will restore river bed elevations, eliminate channel incision, and subsequently arrest channel widening that is degrading aquatic habitat and threatening to dewater over 600 acres of off channel wetlands in the vicinity of and including Heron Pond. The weirs will be constructed by placing graded stone across the width of the river. Project was submitted for review on 2-1-01.

  • Pekin Lake
    0100811 - The Delta Environmental Consultants, Inc. have requested permission to drill one or more ground water monitoring wells at this site. The borings would be 8" in diameter and extend a maximum 40' below present ground level. After soil and/or groundwater samples are taken, the borings will be either backfilled with native soil, or completed as semipermanent groundwater monitoring wells. Project was submitted for review on 1-31-01.

  • Weldon Springs State Park
    0100392 - This project will provide for the construction of a new entrance road, new access roads to Black Locust group camp, the tent/trailer campground and concession and four new parking areas. The material removed for the northern sections of road will be used to construct a dam for a four acre pond/siltation basin. Additional work will include landscaping, removal of two sections of existing road, realignment of three sections of the campground road and the intersection with the old entrance, five new campsites, a campground host site and a new trailer dump station. Project was submitted for review on 1-12-01.

  • Hennepin Canal
    0100387 - This project includes the construction of 17 new IDNR standard concrete block vault toilets at the site. Concrete sidewalks will be provided at each of the sites. Also included in the work will be the demolition of 22 existing toilets, grading and landscaping. Project was submitted for review on 1-12-01.

  • Hennepin Canal
    0009362 - This project will propose to modify the structure of the bridge at Lock 2. Minor earthwork and trail construction will be necessary to connect the north side of the bridge to the adjacent parking area.. The total affected area is 20' x 50'. Project was submitted for review on 12-13-00.

  • Hennepin Canal
    0100390 - This project will include the resurfacing of all of the existing roads and parking areas at the Mautino Fish & Wildlife Area. The road system at this site will also be extended to provide access to three additional lakes. The project will also include upgrading of existing access drives and parking lots at twelve additional sites along the canal. Project was submitted for review on 1-12-01.

  • Mermet Lake Fish and Wildlife Area
    0100302 - This project involves the cleaning of approximately 6000' of Tucker Ditch located at the northwest corner of the site. The ditch is now impeding water flow from the waterfowl area and 1' to 2' of silt needs to be removed. The material removed will be placed on top of the earthen levee which runs parallel to the ditch. Project was submitted for review on 1-8-01.

  • Moraine Hills State Park
    0009421 - The objectives of this project, located at the Kettle Moraine Nature Preserve, are to enhance the wetland soils and promote the establishment of a balanced native flora through the removal of aggressive exotic species and the restoration of the area's hydrology. Activities will include the physical removal of the larger diameter trunks and dense stands of woody vegetation, the selective herbiciding of the invasive exotics, and the removal of the extensive system of farm drainage tiles and ditches. Project was submitted for review on 12-22-00.

  • Sangchris Lake
    0007303 - This project will involve the placement of rip rap along the shoreline in the Hickory Point Campground for bank stabilization purposes. The bank will be reshaped as necessary to allow the placement of the metal baskets that will hold the rip rap. Project was submitted for review on 10-4-00.

  • Hennepin Canal
    0009418 - This project involves the licensing of Touch America to directionally bore a fiber optic telephone line under the Canal south of Feederline Bridge #55. Touch America has permission from AT & T to use their ROW under a DNR license already on file. Project was submitted for review on 12-21-00.

  • Red Hills State Park
    0006571 - This project will replace old and unsafe play equipment at the North Wind and Halfway Picnic Areas at the site. Areas to be impacted will be approximately 100' x 75' at the North Wind area and 75' x 45' at the Halfway area. Project was submitted for review on 9-11-00.

  • Red Hills State Park
    0100086 - As with the project described above, this work will involve the placement of play equipment at the Veterans Point Picnic Area. The area to be impacted will be approximately 100' x 75' in size. Project was submitted for review on 1-4-01.

  • Silver Springs State Park
    0100094 - This project entails the repairing of the supporting earth foundations of the Rob Roy Creek Bridge at the site. Work will include the lifting of the bridge, the regrading of the eroding banks, the installation of geotechnical fabric and stone rip rap on the regraded creek banks, and the resetting of the bridge on the repaired site. Project was submitted for review on 1-5-01.

  • Jubilee College State Park
    0009419 - This project involves the realignment of Thousand Dollar Road by the county where it crosses Jubilee Creek. A new bridge will be constructed on the new alignment and the old alignment will be returned to stream side habitat. Project was submitted for review on 12-22-00.

Questions and Comments
All questions and comments about the environmental review process or this newsletter should be directed to:

    Illinois Department of Natural Resources
    Div. of Natural Resource Review & Coordination
    524 S. Second Street,
    Springfield, IL 62701

    Phone: 217/785-5500

__________________________________________________

The Illinois Department of Natural Resources receives federal financial assistance and therefore must comply with federal anti-discrimination laws. In compliance with the Illinois Human Rights Act, the Illinois Constitution, Title VI of the 1964 Civil Rights Act, Section 504 of the Rehabilitation Act of 1973 as amended, and the U.S. Constitution, the Illinois Department of Natural Resources does not discriminate on the basis of race, religion, color, sex, national origin, age or disability. If you believe you have been discriminated against in any program, activity or facility please contact the Equal Employment Opportunity Officer, Department of Natural Resources, One Natural Resource Way, Springfield, IL 62702-1271, (217) 782-7616, or the Office of Human Resources, U.S. Fish & Wildlife Service, Washington, D.C. 20240.



All public meetings conducted by the Department of Natural Resources will be accessible to persons with disabilities in compliance with Executive Order No. 5 and pertinent state and federal laws, upon notification of the anticipated attendance. Persons with disabilities planning to attend and needing special accommodations should inform the Department of Natural Resources at least five days prior to the meeting by telephoning or writing the Equal Employment Opportunity Officer, Department of Natural Resources, One Natural Resource Way, Springfield, IL 62702-1271, phone (217) 782-7616.

Department of Natural Resources information is available to the hearing impaired by calling DNR's TTY: 217/782-9175. The Ameritech Relay Number is 800/526-0844. Printed by the Authority of the State of Illinois. 362-6/97

 

 

IDNR Homepage   Illinois State Homepage   Link to the Governor's Homepage

IDNR Homepage | Illinois State Homepage | Link to the Governor's Homepage